Inditex's factory audit results will have four levels: Class A, Class B, Class C, and Class D.
Level A will be re-reviewed within 24 months. If the customer has doubts about the various information for the first time, it might immediately review whether he is cheating.
Class B will be reviewed again within 18 months.
Class C, will be re-reviewed within 12 months.
Class D, unqualified factories, will give opportunities for improvement. It will be reviewed again after 6 months.
If it fails, the factory will not be used. However, in the case of improvements, D-class factories still have to be obtained. The customer will give another chance to improve. If it does not pass, it will enter the blacklist.
Special Note: When scoring, if the score is higher, it means that the probability of failure is higher. Because there is a place for disqualification, it will add points.